LMA CONSTRUCTION ADVISORY CORRECTION: Fenway Portal Project - Weekend Bus Shuttles January - March

You are subscribed to the Green Line D Track and Signal Replacement Project from the MBTA.

Fenway Portal Project - Correction: MBTA Green Line D Evening & Weekend Bus Shuttles between Reservoir and Kenmore in January – March

The MBTA is scheduled to replace Green Line D service with bus shuttles between Reservoir and Kenmore on the following weekends:

  • January 5 & 6
  • January 12 & 13
  • January 19 & 20
  • January 26 & 27
  • February 2
  • February 9 & 10
  • February 16 & 17
  • February 23 & 24
  • March 2 & 3
  • March 9 & 10
  • March 23 & 24

The weekend work will take place along the Green Line D Branch in the vicinity of Fenway Station between 2:00 AM Saturday and 5:00 AM Monday morning. These diversions are required for flood construction activities related to the Fenway Portal Project. Customers should anticipate adding 15 minutes to their normal trip during this time.

Due to narrow roads near Beaconsfield, shuttles cannot safely stop there. If you normally access the Green Line at Beaconsfield, there are 2 Green Line stations within walking distance:

Visit mbta.com/alerts for the latest service alerts.

For all queries and concerns regarding the Fenway Portal Project, please contact FenwayPortalProject@mbta.com.

To avoid missing notices or information on the project, please make sure you are signed up for email updates.

If you own or manage a rental property, please share this information with your tenants. We can also provide this information in alternate languages.

For more information:

The schedule for this infrastructure project is weather dependent and subject to change without notice.