LMA CONSTRUCTION ADVISORY: Boylston St. between Park Dr. and Jersey St. - National Grid pipe installation 8/1/19-11/14/19 (9am-3:30pm)

Re:           

National Grid pipe installation on Boylston St. between Park Dr. and Jersey St. from August 1, 2019 to November 15, 2019, weekdays between 9:00 am and 3:30 pm

Scope:

From August 1, 2019 to November 15, 2019, weekdays between 9:00 am and 3:30 pm, Feeney Brothers, on behalf of National Grid, will be installing gas relay lines on Boylston St. between Park Dr. and Jersey St.

Traffic/Other Impacts/Mitigation:

The excavation will occupy two southbound lanes on Boylston St. between Park Dr. and Jersey St.

  • Boylston St. will be reduced to one lane in each direction.
  • There will be no street parking on the southbound side.
  • Police details will be on site to direct vehicular and pedestrian traffic.
  • Signage and barriers will be provided as needed.

Schedule:

August 1, 2019 to November 15, 2019, weekdays between 9:00 am and 3:30 pm