LMA CONSTRUCTION ADVISORY: Binney St. Lane Closure - DFCI Crane Setup, Sat. 8/10/19 (6am-1pm)

Re:           

Binney St. – DFCI Crane Setup, Saturday, August 10, 2019 from 6:00 am to 1:00 pm

Scope:

On Saturday, August 10, 2019 from 6:00 am to 1:00 pm, JC Higgins, on behalf of DFCI, will have a crane setup on Binney St. near Longwood Ave.

Traffic/Other Impacts/Mitigation:

The crane will occupy both travel lanes on Binney St. between Longwood Ave. and the DFCI Loading Dock

  • Through traffic will be detoured to Brookline Ave.
     
  • Pedestrian access will be maintained at all times.
     
  • Access to the BCH ambulance entrance and loading dock will be maintained at all times.
     
  • Police Details will be on-site to direct pedestrian and vehicular traffic.
     
  • Signage, cones and barriers will be provided as needed.
     
  • Crane height will be 170.6’.

Schedule:

Saturday, August 10, 2019 from 6:00 am to 1:00 pm