Francis St. Lane Restriction

Re:
Francis St. Lane Restriction – BWSC Water Main Replacement Project Starts on Tuesday, July 14, 2020 from 9:30 AM to 3:30 PM

Scope:
Starting on Tuesday, July 14, 2020 from 9:30 AM to 3:30 PM, Fed Corp, on behalf of BWSC, will begin work on the water main replacing along Francis St. between Huntington Ave. and Vining St.

Traffic/Other Impacts/Mitigation:
The work will begin near Huntington Ave. and continue down Francis St. towards Vining St.

  • Two-way through traffic will be maintained at all times.
  • Access to BWH driveway entrances will be maintained at all times.
  • There will be no parking allowed along Francis St.
  • Police details and field staff will be on the site to manage vehicular and pedestrian traffic.
  • Signage, cones, and barriers will be provided as needed.

Schedule:
Tuesday, July 14, 2020 to Wednesday, August 19, 2020, from 9:30 AM to 3:30 PM (Weekdays only)