Mercury Work Group
Phase II Reports >> Facilities Loadings

Facilities Loadings | Pretreatment Manual | Tech. Identification
Hg Management Guidebook | Mercury Products Database

For more information, contact David Eppstein by email at
deppstein@masco.harvard.edu, or by calling 617-632-2860.

 
8.0 PHASE I LOADINGS REVIEW (29 HOSPITALS)

One of our goals was to review the mercury loadings calculations performed in Phase I for 29 hospital facilities for Fiscal Year 1995 and to examine corresponding data for the following year to detect any loadings trends. While the Phase I study examined a total of 76 sampling locations within these facilities, discharge loadings were not calculated for locations that had no mercury concentration test data.7 There were no mercury concentration data for 16 sampling locations in the first half-year of FY 1995 and for 29 locations in the second half-year.

For our review, we extracted the applicable loadings data for the same 76 sampling locations from the spreadsheets described above and created Table E-1 of Appendix E that presents the FY 1995 mercury loadings. Similarly, we created Table E-2 of Appendix E to present the corresponding FY 1996 mercury loadings. As in the Phase I study, we did not estimate discharge loadings from sampling locations without mercury concentration test data, i.e., we included only "known" loadings. Refer to Table 8 for a summary comparison of the two studies.

As shown in Table 8, Phase I had estimated that the mercury discharge loadings from 29 hospital facilities contributed between 2.6 and 3.6 percent of total estimated MWRA system loadings during FY 1995. In contrast, our Phase II results suggest that the contribution was between 0.65 and 0.91 percent.

The difference in estimated discharge loadings for FY 1995 is primarily attributable to the detailed flow estimating procedure of our study that produced many lower than previously estimated facility discharge flows. In the Phase I study, for example, the sum of estimated facility discharge flows was 1.18 million gallons per day (MGD) in the first half of FY 1995. In this Phase II study, the corresponding total estimated flow was 0.35 MGD, a difference of about 70 percent. Besides the flow differences, we found a few unexplained differences in the mercury concentration data.

Our study also suggests that estimated FY 1996 mercury discharge loadings for the 29 Phase I hospital facilities were higher than those of FY 1995. From about 0.65 to 0.91 percent in FY 1995, our estimated FY 1996 mercury discharge loadings for the 29 hospitals ranged from about 1.8 to 2.5 percent of the estimated MWRA total system loading.

TABLE 8
ESTIMATED MERCURY DISCHARGE LOADINGS
FROM 29 SELECTED HOSPITALS
PHASE I STUDY (1995) VERSUS PHASE II STUDY

Period of Year

Phase I
FY 1995
Loadings1 (Pounds/Day)

As % of Total System Load 2

Phase II
FY 1995
Loadings 3
(Pounds/Day)

As % of Total System Load 2

Phase II
FY 1996
Loadings 3
(Pounds/Day)

As % of Total System Load 2

1ST HALF

0.040

5.2%

0.006 - 0.007

0.8 - 0.9 %

0.020 - 0.021

2.4 - 2.5 %

2ND HALF

0.029

3.8%

0.005 - 0.007

0.6 - 0.9 %

0.015 - 0.016

1.8 - 1.9 %

    1 Phase I Loadings were taken from tables entitled "Review of SMART Database, Q1 & Q2, Fiscal, 1995" and "Review of SMART Database, Q3 & Q4, Fiscal, 1995" in the End of Pipe Alternatives Subcommittee Final Report, June 1995.

    2 Estimated Total System Mercury Loading was 0.77 pounds/day for Fiscal Year 1995 and 0.83 pounds/day for Fiscal Year 1996 (from background data prepared for the MWRA Industrial Waste Report No. 12, October 1996).

    3 Refer to Appendix E, Tables E-1 and E-2, for Phase II loadings calculations for Fiscal Years 1995 and 1996, respectively.

Note: In the Phase I study, the sum of estimated facility discharge flows was 1.18 million gallons per day (MGD) from 60 sampling locations in the first half of FY 1995 and 0.82 MGD from 47 locations in the second half. In this Phase II study, the sum of estimated facility discharge flows was 0.35 MGD from 51 sampling locations and 0.38 MGD from 62 locations, respectively.

For FY 1996, first and second half-year loadings in Phase II were contributed by 65 and 61 sampling locations, respectively.

    7Thus, the Phase I loadings estimates could be called the estimated "known" loading of the 29 hospital facilities.

 

RETURN TO FACILITIES LOADINGS REPORT
TABLE OF CONTENTS
 

 
ABOUT MASCO, INC. :: AREA PLANNING & DEVELOPMENT
PARKING & TRANSPORTATION SERVICES :: COMMUTEWORKS ::  MASCO SERVICES, INC.
375 LONGWOOD AVE. :: COLLEGES OF THE FENWAY :: CHILD CARE CENTER
MERCURY WORK GROUP :: MASCO MEMBER INSTITUTIONS :: QUARTERLY UPDATE
DIRECTIONS :: THE LONGWOOD MEDICAL AND ACADEMIC AREA
SITE GUIDE :: CONTACT MASCO, INC. :: RETURN HOME

08/16/2006

Copyright © 2000 MASCO, Inc.
375 Longwood Avenue
Boston, MA 02215
Phone: 617-632-2310
Fax: 617-632-2759