MWRA/MASCO Hospital Mercury Work Group
Infrastructure Subcommittee Maintenance Guidebook

This Manual is Intended As a Guideline for the Cleaning of "Special Waste" Piping and Pretreatment Systems for Control of Mercury and is Presented to the MWRA/MASCO Work Groups by Beth Israel Hospital, 330 Brookline Avenue, Boston, Massachusetts, 02115.

TABLE OF CONTENTS

Acknowledgements
 

1.0  PROBLEM OVERVIEW
1.1 Purpose
1.2 General Findings
 
 
2.0  SPECIAL WASTES PIPING AND PRETREATMENT SYSTEMS
2.1 Definition of Special Waste
2.2 Special Waste Piping Design
2.3 Special Waste Regulatory Guidelines
2.3.1 General
2.3.2 Design and Installation of Special Waste Systems
2.3.3 Neutralizing Sumps (Chip Tanks)
2.3.4 pH Adjustment Tanks
 
3.0  FORMS OF MERCURY
3.1 Purpose
3.2 Types of Mercury
3.2.1 Mercury the Element
3.2.2 Elemental Mercury (Hg 0)
3.2.3 Methyl Mercury (CH3Hg+)
3.2.4 Dimethyl Mercury (CH3)2Hg
3.2.5 Divalent Mercury (Hg 2+)
3.3 Use of Mercury
3.3.1 Mercury Products
 
4.0  MERCURY ACCUMULATION IN BIOMASS
4.1 General
4.2 Biomass Formation
4.3 Biomass Absorption of Mercury
4.4 Mercury Accumulation Process
4.5 Dimethyl Mercury Precautions
 
5.0  SPECIAL WASTE RISER
5.1 Purpose
5.2 Riser Diagram
5.2.1 Facility Audit
5.2.2 System Designs and Modifications
5.2.3 Isolation Valves
5.2.4 Sampling Port / Drain Leg
5.2.5 Riser Venting
5.2.6 Glass Inspection Segment
5.2.7 Chemical Reactions of Incompatible Materials
5.2.8 Support Engineering Drawings
  
6.0  TRAP CLEANING PROTOCOL
6.1 Purpose
6.2 Trap Location / Identification
6.3 Removal of Elemental Mercury
6.4 Removal of Biomass
6.5 Cleaning Procedures
 
 
7.0  INFRASTRUCTURE POWERWASHING
7.1 Purpose
7.2 Powerwashing Operations
7.2.1 Cleaning Operations
7.2.2 Powerwashing Precautions
7.2.3 Wastewater Disposal

7.3 Equipment

7.3.1 KJ-1250 Water Jetter
7.4 Chemicals used
7.4.1 Chemical Addition
7.4.2 Bleach Solution
7.4.3 Other Cleaning Chemicals
 
8.0  CHEMICAL CLEANING
8.1 Purpose
8.2 Plumbing Sample Procurement From Host Institutions
8.3 Bench Testing and Chemical Cleaning
8.3.1 Protocol Cleaning Chemicals
8.3.2 Protocol Samples
8.3.3 Summary of Protocol Analytical Data
8.3.4 Sulfuric Acid
8.3.5 Hydrogen Peroxide and Hydrogen Peroxide/Sulfuric Acid Etch
8.3.6 Potassium Hydroxide and Sodium Hydroxide
8.3.7 Nitric Acid and Triton X-100
8.4 Conclusion
 
 
9.0  SAMPLING
9.1 Sampling Techniques
9.1.1 Grab Sample
9.1.2 Composite Sample
9.1.3 Permit Sampling
9.2 Standard Operating Procedures for Sampling
9.3 SMART Data
9.4 Sampling Port
 
  
10.0  WASTE DISPOSAL PROTOCOL
10.1 Purpose
10.2 Waste Disposal Procedures
10.2.1 Mercury Limits
10.2.2 Waste Determination
10.2.3 Waste Disposal

APPENDICES

For further information on appendices that are not currently linked here, please contact David Eppstein by email at deppstein@masco.harvard.edu or by phone at 617-632-2860. Thank you.

  • Appendix A MWRA Standard Operating Procedures for Sampling
     
  • Appendix B DEP Certified Independent Laboratories, February, 1995
    (Contact the DEP, Lawrence Experiment Station, for current listing, updated biannually)
     
  • Appendix C KJ-1250 Water Jetter
     
  • Appendix D MASCO Pipe Cleaning Protocol
     
  • Appendix E Flowmeter Signal Connection Information
     
  • Appendix F SMART Data Clarification Letter From Mr. Eugene B. Benson

 
ABOUT MASCO, INC. :: AREA PLANNING & DEVELOPMENT
PARKING & TRANSPORTATION SERVICES :: COMMUTEWORKS ::  MASCO SERVICES, INC.
375 LONGWOOD AVE. :: COLLEGES OF THE FENWAY :: CHILD CARE CENTER
MERCURY WORK GROUP :: MASCO MEMBER INSTITUTIONS :: QUARTERLY UPDATE
DIRECTIONS :: THE LONGWOOD MEDICAL AND ACADEMIC AREA
SITE GUIDE :: CONTACT MASCO, INC. :: RETURN HOME

12/01/2008

Copyright © 2000 MASCO, Inc.
375 Longwood Avenue
Boston, MA 02215
Phone: 617-632-2310
Fax: 617-632-2759